The project began following the disconnection of the irrigation system with the DCPS team removing and temporarily relocating several large planters from the 5th floor balconies. Then, the concrete topping slab was demolished and carefully transported out of the building in manageable sections to minimize disruption.
Once exposed, the existing waterproof membrane was removed from the structural concrete, and the slab was mechanically prepared using grinding and shot blasting. Afterwards, the DCPS team installed a new fluid-applied waterproofing membrane across the full balcony area. Electronic Leak Detection (ELD) testing and third-party inspections were performed to verify waterproofing integrity.
After completing waterproofing, DCPS proceeded with the installation of a drainage composite layer to promote proper water flow and protect the membrane by directing moisture to drainage points.
To complete the project, the irrigation system was restored, and the salvaged planters were returned to their original locations with the help of a pedestal paver system. The finished work resolved the water intrusion issues and provided the residents with a restored outdoor space built for long-term performance.