For the epoxy flooring installation, DPCS began the two week-long process by removing the existing tile and sheet-welded vinyl floor down to the concrete substrate. Next, the team mechanically prepared the floor using a diamond grinder to achieve a CSP2-3 finish, optimal for a resinous flooring system. To achieve a proper bond, an application of epoxy primer was applied. Following the primer, a custom design was created by applying a base coat of epoxy and broadcasting custom color chip flakes to create the desired texture, color, and design, agreed upon with the architectural design team. The custom design required multiple colors and patterns to be incorporated along with two topcoats of clear polyaspartic to seal it and achieve the required finish.
In the other phase of work, the sea lion exhibit pathways required swift and strategic execution. After having just one week to plan and procure materials, the DCPS team completed demolition and debris removal in under four days while working exclusively outside of zoo operating hours. Concrete foundations and ADA-compliant ramp walls were installed immediately after. Stair and paving work was prioritized to allow the welding team to begin railing fabrication. Despite weather challenges and access restrictions, the DCPS team poured roughly 100 cubic yards of concrete in one week, completing the project just in time for the scheduled grand opening.
Both projects significantly improved the zoo’s visitor experience and facility performance. The flooring provided a durable, low-maintenance surface, while the new pathways and viewing areas improved safety and created a visually cohesive visitor experience.