Mountain Timeshare Property

Full unit renovation across 22 units and 68 bathrooms


Mountain Timeshare Property

A mountain timeshare property that was in need of unit renovation, including installation of new tile, vanities, showers, bathtubs, paint and flooring.

Location

Breckenridge, CO

Summary

Full renovation of 68 bathrooms across 22 timeshare units within an aggressive 8-week window. The scope included demolition and installation of new tile, vanities, showers, bathtubs, paint, and flooring.


Challenge

The property sought to refresh and modernize bathrooms across its timeshare units to enhance guest experience and maintain competitive appeal. The property’s age introduced extensive plumbing issues and hidden structural deficiencies. In addition, the project had to be completed within a strict 8-week window during the resort’s off-season, compounded by national material shortages.

Solution

The DCPS team executed the remodel through a carefully sequenced plan that prioritized communication, coordination, and adaptability. Demolition and installation followed a phased approach to maintain steady progress and avoid delays. When faced with unforeseen plumbing issues and material shortages, the team adapted quickly and kept the client informed throughout.


The project proceeded through carefully planned phases, beginning with demolition of existing bathroom finishes — tile, bathtubs, vanities, and showers — across all units. Given the age of the property, each unit revealed its own set of challenges, like structural deficiencies and plumbing issues. These problems were addressed immediately to avoid slowing down the overall schedule.

Once demolition was complete, the installation phase began. New finishes were brought in and installed efficiently. The installation scope included new bathtubs and showers, updated tile, modern vanities, fresh paint, and new flooring. The updates elevated the look and feel of each unit, aligning with the property’s goal of enhancing guest comfort and maintaining a high standard of appearance.

Frequent communication and coordination were essential throughout the project. With a hard deadline and no flexibility on timelines, the DCPS team maintained close contact with the client and adapted quickly when faced with unexpected challenges, including material shortages. These efforts helped keep the project on track and ensured successful delivery within the tight 8-week window.