The project began with an assessment of the trees, surrounding structures, utility lines, traffic patterns, and other site conditions that would affect safe execution. Because portions of the work extended into the public right-of-way, the team secured the necessary City and County of Denver permit and developed plans for lane and sidewalk closures. Traffic control and flaggers were coordinated to help protect the crew while maintaining safe movement for vehicles, pedestrians, and cyclists around the work zone. Equipment and crew logistics were planned carefully due to the limited working area and the proximity of the church’s stained-glass windows, utility lines, neighboring businesses, and active streets. The field team then completed the planned tree removals, stump removals, hazardous deadwood pruning, and utility clearance using multiple pieces of specialized equipment. Throughout the multi-day project, project leadership and field crews adjusted operations as needed to maintain a controlled work zone and keep the project moving safely and efficiently.